"Construction has begun on twinning the first section of Hwy. 63 south of Fort McMurray, Alta. from Hwy 69 to south of Hwy. 881" **
Sweet facts:
Budget : $940M
Project : 224 kilometres of twinning south of Hwy. 881
Expected date of completion: Fall 2008
Sweeter facts:
$ 4,196,428.57142857 per Km
June 21, 2007 (or 20th?) - Sept 22, 2008 (458 days)
Thats: 0.489082969432314 or .49km/day
or
2.04464285714286 days per KM
or 2 days & .04 days (57 mins, 36 secs) for each KM
** Read More from TruckNews
Sweet facts:
Budget : $940M
Project : 224 kilometres of twinning south of Hwy. 881
Expected date of completion: Fall 2008
Sweeter facts:
$ 4,196,428.57142857 per Km
June 21, 2007 (or 20th?) - Sept 22, 2008 (458 days)
Thats: 0.489082969432314 or .49km/day
or
2.04464285714286 days per KM
or 2 days & .04 days (57 mins, 36 secs) for each KM